BUA-Phase 1 |
20000 |
|
Rate per sq. ft. (in INR) |
Total cost (in lacs INR) |
Building (2nd Floor and Trus) 10000 SFT |
1500 |
150 |
Mechanical, Electrical & Plumbing |
1900 |
380 |
Interior finishing & External development |
600 |
120 |
Medical equipment |
2500 |
500 |
Non-medical equipment & furniture |
250 |
50 |
Cath Lab |
|
200 |
Total |
1400 |
BUA-Phase 2 |
20000 |
Civil Works - Building cost |
2000 |
400 |
Mechanical, Electrical & Plumbing |
1200 |
240 |
Interior finishing & External development |
600 |
120 |
Medical equipment |
2500 |
120 |
Non-medical equipment & furniture |
250 |
50 |
Total |
930 |
Grand Total |
2330 |